Project Updates

08/25/10: The project is ready to be photographed.

08/19/10: Final tile shipped, unbroken and behind schedule but completely installed and finished. 

08/09/10:  The final shipment of custom encaustic tile has arrived on Martha's Vineyard for installation in the kitchen. The landscape has been installed and the house is being prepared for photographic documentation.

07/12/10: TCM tile confirmed to be produced and shipped this week. (Molly Knight)

07/04/10: Landscape installed, Interior tile installed. Missing tiles ordered, photo and video documentation complete.

6/02/10: The interior designers arrive to organize and install the house.